[1]叶丹.公路下穿施工对高速铁路桥梁墩台及行车安全影响研究[J].高速铁路技术,2024,15(03):13-18.[doi:10.12098/j.issn.1674-8247.2024.03.003]
 YE Dan.Research on the Impact of Road Undercrossing Construction on the Pier Foundations and Operational Safety of High-speed Railway Bridges[J].HIGH SPEED RAILWAY TECHNOLOGY,2024,15(03):13-18.[doi:10.12098/j.issn.1674-8247.2024.03.003]
点击复制

公路下穿施工对高速铁路桥梁墩台及行车安全影响研究()
分享到:

《高速铁路技术》[ISSN:1674-8247/CN:51-1730/U]

卷:
15卷
期数:
2024年03期
页码:
13-18
栏目:
理论探索
出版日期:
2024-06-20

文章信息/Info

Title:
Research on the Impact of Road Undercrossing Construction on the Pier Foundations and Operational Safety of High-speed Railway Bridges
文章编号:
1674-8247(2024)03-0013-06
作者:
叶丹
中铁工程设计咨询集团有限公司, 北京 100055
Author(s):
YE Dan
China Railway Engineering Design and Consulting Group Co. ,Ltd. ,Beijing 100055 ,China
关键词:
公路施工铁路桥梁现场监测桥墩沉降数值仿真
Keywords:
road constructionrailway bridgeon-site monitoringbridge pier settlementnumerical simulation
分类号:
U455.55+9
DOI:
10.12098/j.issn.1674-8247.2024.03.003
文献标志码:
A
摘要:
以怀安县高速铁路车站西路下穿张呼高速铁路怀安站特大桥为例,采用现场监测和数值模拟研究公路下穿施工对怀安站特大桥邻近墩台及行车安全的影响。首先,利用现场监控得到下穿墩台在不同施工阶段的沉降值和横、纵向水平位移值;随后,通过MidasGTS建立数值模型分析墩台的动力响应规律;采用ANSYS/LS-DYNA软件建立列车-轨道动力学耦合模型,评价怀安特大桥列车在公路下穿施工过程中的行车安全性。研究结果表明:在车站西路下穿施工过程中,怀安站特大桥桥墩沉降和位移条件均在规范限值内;为确保列车运行的绝对安全与平稳,建议怀安特大桥高速铁路列车限速200km/h通过施工区段。
Abstract:
Taking the example of Huai’an County High-speed Railway Station West Road undercrossing the Huai’an Station Super Major Bridge of the Zhangjiakou-Hohhot High-speed Railway,this study investigates the impact of the construction on the adjacent piers of the Huai’an Station Super Major Bridge. Firstly,on-site monitoring was employed to obtain the settlement values and lateral and longitudinal horizontal displacement values of the underpass pier at various construction stages. Subsequently,a numerical simulation model was established using Midas GTS to further analyze the dynamic response behavior of the pier. Finally,a coupled train-track dynamics model was developed in ANSYS/LS-DYNA to evaluate the train operational safety during the road construction. The research findings indicate that during the road construction,the settlement and displacement of the piers of the Huai’an Station Super Major Bridge remain within the specified limits. It is recommended,for the absolute safety and smooth operation of trains,to appropriately limit the speed of high-speed trains to 200 km/h when traversing the construction section of the Huai’an Station Super Major Bridge.

参考文献/References:

[1] 谢毅,肖杰. 高速铁路发展现状及趋势研究[J]. 高速铁路技术, 2021,12(2):23-26. XIE Yi,XIAO Jie. Research on High-speed Railway Development Status and Trend[J]. High Speed Railway Technology,2021, 12(2):23-26.
[2] 翟婉明,姚力,孙立,等. 基于车辆-轨道耦合动力学的400 km/h高速铁路线路平面参数设计研究[J]. 高速铁路技术,2021, 12(2):1-10,16. ZHAI Wanming,YAO Li,SUN Li,et al. Research on Route Plan Design Parameters of 400 km/h High-speed Railway Based on Vehicle-track Coupling Dynamics[J]. High Speed Railway Technology,2021,12(2):1-10,16.
[3] 陈兆玮,翟婉明. 基于列车振动的高速铁路桥墩沉降控制阈值[J]. 交通运输工程学报,2022,22(2):136-147. CHEN Zhaowei,ZHAI Wanming. Control Threshold of Pier Settlement in High-speed Railways Based on Train Vibrations[J]. Journal of Traffic and Transportation Engineering,2022,22(2):136-147.
[4] 龚循强,汪宏宇,鲁铁定,等. 基于RLM-MC的高速铁路桥墩沉降曲线预测方法[J]. 铁道学报,2022,44(10):142-149. GONG Xunqiang,WANG Hongyu,LU Tieding,et al. A Settlement Curve Prediction Method of High-speed Railway Bridge Pier Based on RLM-MC[J]. Journal of the China Railway Society,2022,44(10):142-149.
[5] 董亮,苏永华,袁磊. 地面堆卸载作用对铁路桥墩沉降的影响分析[J]. 铁道建筑,2019,59(5):51-55. DONG Liang,SU Yonghua,YUAN Lei. Influence of Ground Surcharge and Unloading on Settlement of Railway Bridge Pier[J]. Railway Engineering,2019,59(5):51-55.
[6] 周济民. 盾构区间隧道下穿高架桥桩基群施工技术与环境影响预测[J]. 现代隧道技术,2016,53(1):165-172. ZHOU Jimin. Construction Technology and Environmental Impact Prediction for a Shield Tunnel under a Viaduct Pile Foundation Group [J]. Modern Tunnelling Technology,2016,53(1):165-172.
[7] 孟长江,熊大生,赵海粟,等. 基坑降水对临近运营高铁桥墩的影响评估分析[J]. 岩土工程学报,2014,36(S2):265-268. MENG Changjiang,XIONG Dasheng,ZHAO Haisu,et al. Evaluation and Analysis of the Influence of Foundation Pit Dewatering on the Adjacent High-speed Rail Pier[J]. Chinese Journal of Geotechnical Engineering,2014,36(S2):265-268.
[8] 蒋小锐,黄杰,李楠. 城际铁路明挖隧道下穿既有高铁施工控制技术及标准探讨[J]. 铁道标准设计,2020,64(6):104-111. JIANG Xiaorui,HUANG Jie,LI Nan. Discussion on Construction Control Technology and Standard of Intercity-railway Undercrossing Existing High-speed Railway by Open-cut Tunnel[J]. Railway Standard Design,2020,64(6):104-111.
[9] 李士中. 京杭大运河新开挖航道对高速铁路桥墩的影响[J]. 铁道建筑,2020,60(8):33-36. LI Shizhong. Influence of Beijing-Hangzhou Grand Canal’s Newly Excavated Waterway on Bridge Pier of High Speed Railway[J]. Railway Engineering,2020,60(8):33-36.
[10]王国栋,王志杰,段明明,等. 铁路隧道下穿连续刚构桥墩施工影响及防控措施研究[J]. 铁道科学与工程学报,2017,14(11):2399-2406. WANG Guodong,WANG Zhijie,DUAN Mingming,et al. Research on the Construction Influence and Protection of Railway Tunnel Crossing beneath the Pier of Existing Continuous Rigid Frame Bridge [J]. Journal of Railway Science and Engineering,2017,14(11):2399-2406.
[11]TB 10101- 2018 铁路工程测量规范[S]. TB 10101- 2018 Code for Railway Engineering Survey[S].
[12]郭延辉,严明,宋琴,等. 深基坑开挖对临近既有高压天然气管道的影响[J]. 地下空间与工程学报,2021,17(S2):840-847. GUO Yanhui,YAN Ming,SONG Qin,et al. Influence of Deep Foundation Pit Excavation on Adjacent Existing High-pressure Natural Gas Pipeline[J]. Chinese Journal of Underground Space and Engineering,2021,17(S2):840-847.
[13]张碧文. 浅埋盾构下穿高铁路基沉降分析及控制[J]. 现代隧道技术,2013,50(2):109-113,126. ZHANG Biwen. Analysis and Control of High-speed Railway Subgrade Settlement Caused by Shallow-shield Tunnel Construction[J]. Modern Tunnelling Technology,2013,50(2):109-113,126.

相似文献/References:

[1]周川江,徐昕宇,郑晓龙,等.桥墩刚度对铁路大跨连续梁桥车桥耦合振动的影响研究[J].高速铁路技术,2022,13(06):23.[doi:10.12098/j.issn.1674-8247.2022.06.005 ]
 ZHOU Chuanjiang,XU Xinyu,ZHENG Xiaolong,et al.Study on the Influence of Pier Stiffness on Vehicle-bridge Coupled Vibration of Long-span Continuous Girder Bridge of Railway[J].HIGH SPEED RAILWAY TECHNOLOGY,2022,13(03):23.[doi:10.12098/j.issn.1674-8247.2022.06.005 ]
[2]温贵生.灌河特大桥连续钢桁-柔性拱主桥建造技术[J].高速铁路技术,2023,14(01):76.[doi:10.12098/j.issn.1674-8247.2023.01.014]
 WEN Guisheng.Construction Technology of Continuous Steel Truss-flexible Arch Main Bridge of Guanhe Super Major Bridge[J].HIGH SPEED RAILWAY TECHNOLOGY,2023,14(03):76.[doi:10.12098/j.issn.1674-8247.2023.01.014]

备注/Memo

备注/Memo:
收稿日期:2024-03-18
作者简介:叶丹(1983-),男,高级工程师。
更新日期/Last Update: 2024-06-30