[1]李兴龙,蔺文帅.复杂地质条件下矩形顶管下穿管线影响分析[J].高速铁路技术,2023,14(02):94-100.[doi:10.12098/j.issn.1674-8247.2023.02.019]
LI Xinglong,LIN Wenshuai.Impact Analysis for Rectangular Pipe Jacking with Underpass Pipeline Under Complex Geological Conditions[J].HIGH SPEED RAILWAY TECHNOLOGY,2023,14(02):94-100.[doi:10.12098/j.issn.1674-8247.2023.02.019]
点击复制
复杂地质条件下矩形顶管下穿管线影响分析()
《高速铁路技术》[ISSN:1674-8247/CN:51-1730/U]
- 卷:
-
14卷
- 期数:
-
2023年02期
- 页码:
-
94-100
- 栏目:
-
- 出版日期:
-
2023-04-30
文章信息/Info
- Title:
-
Impact Analysis for Rectangular Pipe Jacking with Underpass Pipeline Under Complex Geological Conditions
- 文章编号:
-
1674-8247(2023)02-0094-07
- 作者:
-
李兴龙; 蔺文帅
-
中铁二院北方勘察设计有限责任公司,济南250000
- Author(s):
-
LI Xinglong; LIN Wenshuai
-
China Railway Eryuan North Survey and Design Co. , Ltd. , Jinan? 250000 ,China
-
- 关键词:
-
矩形顶管; 地铁车站; 地下管线; 数值模拟; 影响分析
- Keywords:
-
rectangular pipe jacking; metro station; underground pipeline; numerical simulation; impact analysis
- 分类号:
-
U455
- DOI:
-
10.12098/j.issn.1674-8247.2023.02.019
- 文献标志码:
-
A
- 摘要:
-
为研究矩形顶管施工对邻近管线的影响,以某铁路出入口顶管工程为依托,建立三维数值模型对矩形顶管近接下穿管线过程中管线和地表变形规律进行研究,并结合现场实测数据进行分析。研究结果表明:(1)矩形顶管施工引起的地表变形以沉降为主,隧道上方土体产生了向隧道中心靠拢的趋势,地表沉降最大值16.3mm,位于隧道中间位置,沉降影响范围为20m;(2)受接收井的临空开挖面和施加在始发井的顶推力影响,开挖结束后接收井和始发井地表产生隆起,隆起最大值达到1.95mm;(3)受土体挤压,管线水平位移最大值达到0.64mm;在控制好管线沉降变形同时,也要注意对其施加水平约束,避免水平位移过大导致破坏;(4)管线变形和变形速率均在安全控制指标之内,数值模拟的管线变形规律与实测数据大致相同,数值模拟的地表和各管线变形规律是可信的。
- Abstract:
-
In order to study the impact of rectangular pipe jacking on adjacent pipelines,a three-dimensional numerical model was established in this paper based on a case of pipe jacking at the portals of a railway,to study the deformation law of the pipeline and the ground surface during the process of rectangular pipe jacking approaching the underpass pipeline,and analyze it in combination with the measured data on-site. The results show that:(1)The surface deformation caused by rectangular pipe jacking is mainly settlement,and the soil above the tunnel tends to approach the center of the tunnel. The maximum surface settlement is 16. 3 mm in the middle of the tunnel,and the settlement impact range is 20 m.(2) Affected by the free excavation face of the receiving shaft and the jacking force applied to the launching shaft,the surface of the receiving shaft and the launching shaft uplifts after excavation,with the maximum uplift reaching 1. 95 mm.(3)The maximum horizontal displacement of the pipeline reaches 0. 64 mm due to soil extrusion. While controlling the settlement and deformation of the pipeline,attention should also be paid to applying horizontal restraints to avoid damage caused by excessive horizontal displacement.(4)The deformation and deformation rate of the pipeline are within the safety control index,the deformation law of the pipeline simulated by the numerical method is roughly the same as the measured data,and the deformation law of the surface and each pipeline simulated by the numerical method is credible.
参考文献/References:
[1]旷文涛,陈洲频,刘保林,等. 隧道管幕暗挖法原理及应用探讨[J]. 高速铁路技术,2020,11(6):28 - 33. KUANG Wentao,CHEN Zhoupin,LIU Baolin,et al. Discussion on Principle and Application of the Pipe-curtain Tunneling Method[J]. High Speed Railway Technology,2020,11(6):28 - 33.
[2]喻军,龚晓南. 考虑顶管施工过程的地面沉降控制数值分析[J].岩石力学与工程学报,2014,33(S1):2605 - 2610. YU Jun,GONG Xiaonan. Numerical Analysis of Surface Settlement Control Considering Pipe Jacking Construction Process[J]. Chinese Journal of Rock Mechanics and Engineering,2014,33(S1):2605 -2610.
[3]张文瀚,谢雄耀,李攀. 浅层顶管隧道施工对路基变形影响数值分析[J]. 地下空间与工程学报,2011,7(S2):1619 - 1624, 1652. ZHANG Wenhan,XIE Xiongyao,LI Pan. Numerical Analysis of Deformation of Highway Roadbase Caused by Shallow Underground Pipe Jacking in Sand Soil[J]. Chinese Journal of Underground Space and Engineering,2011,7(S2):1619 - 1624,1652.
[4]赖金星,王开运,侯丹丹,等. 砂土地层顶管施工土体变形规律三维数值分析[J]. 西安科技大学学报,2015,35(4):450 - 457. LAI Jinxing,WANG Kaiyun,HOU Dandan,et al. 3D Numerical Analysis on Displacement Regularity of Pipe Jacking Sewer in Sand Soil Stratum[J]. Journal of Xi’an University of Science and Technology,2015,35(4):450 - 457.
[5]郝小红,郭佳. 考虑超大断面顶管施工过程的地层变形数值分析[J]. 华北水利水电大学学报(自然科学版),2017,38(6):66 -71,81. HAO Xiaohong,GUO Jia. Numerical Analysis of Stratum Deformation Considering Large Section Pipe Jacking Construction Process[J]. Journal of North China University of Water Resources and Electric Power (Natural Science Edition),2017,38(6):66 - 71,81.
[6]黄吉龙,陈锦剑,王建华,等. 大口径顶管顶进过程的数值模拟分析[J]. 地下空间与工程学报,2008,4(3):489 - 493. HUANG Jilong,CHEN Jinjian,WANG Jianhua,et al. Numerical Analysis of Large Diameter Pipe-jacking[J]. Chinese Journal of Underground Space and Engineering,2008,4(3):489 - 493.
[7]张建安. 矩形顶管顶推力对上部地表位移影响规律研究[J]. 城市道桥与防洪,2017(8):266 - 268,278. ZHANG Jian’an. Study on Influence of Jacking Thrust of Rectangular Pipe Jacking on Upper Surface Displacement[J]. Urban Roads Bridges & Flood Control,2017(8):266 - 268,278.
[8]温锁林. 大断面矩形顶管施工对环境影响研究[J]. 中国市政工程,2011(5):37 - 39,89. WEN Suolin. A Study of Environmental Influence Caused by Large Section Rectangular Pipe Jacking Construction[J]. China Municipal Engineering,2011(5):37 - 39,89.
[9]邓长茂,彭基敏,沈国红. 软土地区矩形顶管施工地表变形控制措施探讨[J]. 地下空间与工程学报,2016,12(4):1002 -1007. DENG Changmao,PENG Jimin,SHEN Guohong. Discussion on Control Methods of Ground Surface Settlement Caused by Rectangular Pipe Jacking Construction in Soft Soils[J]. Chinese Journal of Underground Space and Engineering,2016,12(4):1002 - 1007.
[10]WANG Ning,GAO Yi,YU Shaohui,et al. Disturbance of Rectangular Pipe Jacking Tunnel Group Construction on Soil Behind Working Shaft [J]. Tunnel Construction,2019,39(3):413-420.
[11]HE Shanning,DOU Xiaotian,ZHAO Liyong,et al. Analysis of Thrust Force of Adjacent Construction of Shallow-buried Rectangular Pipe Jacking Tunnel Group[J]. Tunnel Construction,2019,39(3):383-390.
[12]HAN Zhanbo,DOU Xiaotian,CAO Weiming,et al. Control Technology for Surface Deformation Induced by Construction of Shallow-covered and Small-spacing Rectangular Pipe Jacking[J]. Tunnel Construction,2019,39(3):496-503.
[13]景路,袁聚云,袁勇. 顶管工程中的地层损失参数和土体变形计算[J]. 岩土力学,2013,34(S1):173-178. JING Lu,YUAN Juyun,YUAN Yong. Ground Loss Parameter and Soil Deformation in Pipe Jacking[J]. Rock and Soil Mechanics, 2013,34(S1):173-178.
[14]汤旅军,陈仁朋,尹鑫晟,等. 密实砂土地层盾构隧道开挖面失稳离心模型试验研究[J]. 岩土工程学报,2013,35(10):1830-1838. TANG Lvjun,CHEN Renpeng,YIN Xinsheng,et al. Centrifugal Model Tests on Face Stability of Shield Tunnels in Dense Sand [J]. Chinese Journal of Geotechnical Engineering,2013,35(10):1830-1838.
[15]唐晓武,李姣阳,邹金杰,等. 浅埋盾构隧道开挖面失稳发展过程模型试验[J]. 浙江大学学报(工学版),2017,51(5):863-869. TANG Xiaowu,LI Jiaoyang,ZOU Jinjie,et al. Model Test of Evolution of Face Instability in Shallow Shield Tunnel[J]. Journal of Zhejiang University (Engineering Science),2017,51(5):863-869.
[16]李姣阳,刘维,邹金杰,等. 浅埋盾构隧道开挖面失稳大比尺模型试验研究[J]. 岩土工程学报,2018,40(3):562-567. LI Jiaoyang,LIU Wei,ZOU Jinjie,et al. Large-scale Model Tests on Face Instability of Shallow Shield Tunnels in Sand[J]. Chinese Journal of Geotechnical Engineering,2018,40(3):562-567.
[17]WANG Hemin,XIAO Zunqun,TANG Dongsang,et al. Numerical Simulation and Field Monitoring of Construction Process of Rectangular Pipe Jacking in No. 1 Underground Passage of Shangdu Road Station on Zhengzhou Metro Line 4[J]. Tunnel Construction, 2019,39(S2):110-119.
[18]张治国,师敏之,张成平,等. 类矩形盾构隧道开挖引起邻近地下管线变形研究[J]. 岩石力学与工程学报,2019,38(4):852-864. ZHANG Zhiguo,SHI Minzhi,ZHANG Chengping,et al. Research on Deformation of Adjacent Underground Pipelines Caused by Excavation of Quasi-rectangular Shields[J]. Chinese Journal of Rock Mechanics and Engineering,2019,38(4):852-864.
备注/Memo
- 备注/Memo:
-
收稿日期:2022-01-03
作者简介:李兴龙(1986-),男,高级工程师。
基金项目:陕西省科技厅社会发展项目(2018SF - 382)
更新日期/Last Update:
2023-04-30