[1]李准,丁梯,罗福君.长工期铁路工程间接费费率优化策略研究[J].高速铁路技术,2023,14(04):19-24,39.[doi:10.12098/j.issn.1674-8247.2023.04.004]
 LI Zhun,DING Ti,LUO Fujun.A Study on Optimization Strategy of Indirect Cost Rate for Railway Projects with a Long Construction Period[J].HIGH SPEED RAILWAY TECHNOLOGY,2023,14(04):19-24,39.[doi:10.12098/j.issn.1674-8247.2023.04.004]
点击复制

长工期铁路工程间接费费率优化策略研究()
分享到:

《高速铁路技术》[ISSN:1674-8247/CN:51-1730/U]

卷:
14卷
期数:
2023年04期
页码:
19-24,39
栏目:
出版日期:
2023-08-30

文章信息/Info

Title:
A Study on Optimization Strategy of Indirect Cost Rate for Railway Projects with a Long Construction Period
文章编号:
1674-8247(2023)04-0019-06
作者:
李准丁梯罗福君
中铁二院工程集团有限责任公司,成都 610031
Author(s):
LI ZhunDING TiLUO Fujun
China Railway Eryuan Engineering Group Co. ,Ltd. ,Chengdu? 610031 ,China
关键词:
铁路工程长工期间接费企业管理费优化策略
Keywords:
railway engineeringlong construction periodindirect costenterprise management feeoptimization strategy
分类号:
F530.31
DOI:
10.12098/j.issn.1674-8247.2023.04.004
文献标志码:
A
摘要:
铁路工程规模的日趋增大和项目工期的逐步增长对与工期有关的费率性费用产生了较大影响。结合间接费已有的研究成果,选取成兰、大瑞、玉磨铁路等典型长工期铁路项目进行现场调研和数据统计,收集现场实际间接费的组成及费用情况,并与理论计算的费用进行对比分析,证明了间接费(特别是企业管理费)应结合项目工期进行调整的合理性,并找出企业管理费中管理人员工资、固定资产使用费等5项受工期影响的因素,针对性地提出了不同工期情况下企业管理费的调整原则、企业及市场相应控制管理措施等结论。研究成果可为铁路相关部门下阶段造价标准修订,准确反映企业管理费、间接费的组成及费用,促进我国铁路建设市场良性发展提供技术支撑。
Abstract:
The increasing scale of railway engineering projects and the gradual increase in project duration have had a significant impact on time-related indirect costs. The paper combined existing study results on indirect costs,selected typical railway projects with long construction periods such as the Chengdu-Lanzhou Railway,Dali-Ruili Railway,and Yuxi-Mohan Railway for on-site investigations and data collection of actual indirect cost composition and cost situation,and compared and analyzed them with theoretically calculated costs. It proves the rationality of adjusting indirect costs (especially enterprise management costs)in combination with the construction period and identifies five factors in enterprise management costs that are affected by the construction period,such as management personnel salaries and fixed asset usage fees. Based on different construction periods,this study proposed principles for adjusting enterprise management costs and other related control measures in the market. The results can provide technical support for the revision of cost standards in the next stage for relevant railway departments,accurately reflect the composition and cost of enterprise management costs and indirect costs,and promote the healthy development of China’s railway construction market.

参考文献/References:

[1]国铁科法〔2017〕30号,铁路基本建设工程设计概(预)算编制办法[S]. Guo Tie Ke Fa〔2017〕No. 30,Compilation Method of Railway Capital Construction Engineering Design Budget[S].
[2]魏永幸,岳志勤,李光辉. 复杂艰险山区地质灾害识别与铁路减灾选线[J]. 高速铁路技术,2019,10(3):1-5,24.
[3]谢正军. 境外投资的高速公路项目其他工程费及间接费综合费率的计取方法研究[J]. 公路交通技术,2018,34(4):136-140. XIE Zhengjun. Study on the Billing Method of the Other Engineering Expenses and Comprehensive Indirect Cost Rate of Expressway Projects Abroad[J]. Technology of Highway and Transport,2018, 34(4):136-140.
[4]王庆玲. 施工企业项目部的间接费控制研究[J]. 企业改革与管理,2017(9):217-218. WANG Qingling. Research on Overhead Cost Control of Project Department of Construction Enterprise[J]. Enterprise Reform and Management,2017(9):217-218.
[5]郭晓晔,刘晓渡. 基于定额借用情况下工程计价软件计算间接费的探讨[J]. 工程造价管理,2018(1):69-72. GUO Xiaoye,LIU Xiaodu. Discussion on Calculation of Indirect Costs of Engineering Pricing Software Based on Quota Borrowing[J]. Engineering Cost Management,2018(1):69-72.
[6]国铁科法〔2017〕31号,铁路基本建设工程设计概(预)算费用定额[S] . Guo Tie Ke Fa〔2017〕No. 31,Budget Cost Quota of Railway Capital Construction Engineering Design[S].
[7]李源. 工程项目工期与成本控制协调机理研究[D]. 西安:西安科技大学,2005. LI Yuan. Study on Control Coordination Mechanism of Schedule and Cost in Engineering Project[D]. Xi’an:Xi’an University of Science and Technology,2005.
[8]李准,张穷. 浮动平均值在大变形隧道定额测定与分析中的应用[J]. 高速铁路技术,2022,13(1):60-63. LI Zhun,ZHANG Qiong. Application of Floating Average Value in Quota Determination and Analysis of Large Deformation Tunnel[J]. High Speed Railway Technology,2022,13(1):60-63.
[9]胡兴华. 建设工程工期索赔问题研究[D]. 武汉:湖北工业大学, 2016. HU Xinghua. Research on the Claim of Construction Period[D]. Wuhan:Hubei University of Technology,2016.
[10]李准,张路刚. 西部山区铁路隧道涌水抽排施工方案探讨[J].高速铁路技术,2018,9(4):88-92. LI Zhun,ZHANG Lugang. Discussion on Tunnel Water-burst Pumping and Drainage Construction Scheme of Western Mountain Railway[J]. High Speed Railway Technology,2018,9(4):88-92.

相似文献/References:

[1]王哲威,冯 涛,杜宇本,等.地质横断面选线技术在铁路工程中的应用[J].高速铁路技术,2022,13(06):69.[doi:10.12098/j.issn.1674-8247.2022.06.013 ]
 WANG Zhewei,FENG Tao,DU Yuben,et al.Application of Geological Cross-section Route Selection Technology in Railway Engineering[J].HIGH SPEED RAILWAY TECHNOLOGY,2022,13(04):69.[doi:10.12098/j.issn.1674-8247.2022.06.013 ]
[2]陈建国.基于实景图的铁路大、小型临时工程界面及投资划分研究[J].高速铁路技术,2023,14(03):37.[doi:10.12098/j.issn.1674-8247.2023.03.008]
 CHEN Jianguo.A Study on Interface and Investment Division of Large and Small Temporary Works of Railway Based on the Real Picture[J].HIGH SPEED RAILWAY TECHNOLOGY,2023,14(04):37.[doi:10.12098/j.issn.1674-8247.2023.03.008]
[3]刘伟,周超,金俊俊.不同地质雷达设备在铁路工程隐伏岩溶探测中的应用与对比[J].高速铁路技术,2024,15(04):82.[doi:10.12098/j.issn.1674-8247.2024.04.015]
 LIU Wei,ZHOU Chao,JIN Junjun.Application and Comparison of Different Ground Penetrating Radar Systems in the Detection of Concealed Karst in Railway Engineering[J].HIGH SPEED RAILWAY TECHNOLOGY,2024,15(04):82.[doi:10.12098/j.issn.1674-8247.2024.04.015]

备注/Memo

备注/Memo:
收稿日期:2022-06-01
作者简介:李准(1982-),男,高级工程师。
更新日期/Last Update: 2023-08-30