[1]刘发明,游励晖.西南艰险山区铁路桥梁防冲刷设计[J].高速铁路技术,2017,8(06):93-98.[doi:10.12098/j.issn.1674-8247.2017.06.019]
 LIU Faming YOU Lihui.Scour Prevention Design of Railway Bridge in Southwest Dangerous Mountainous Area[J].HIGH SPEED RAILWAY TECHNOLOGY,2017,8(06):93-98.[doi:10.12098/j.issn.1674-8247.2017.06.019]
点击复制

西南艰险山区铁路桥梁防冲刷设计()
分享到:

《高速铁路技术》[ISSN:1674-8247/CN:51-1730/U]

卷:
8卷
期数:
2017年06期
页码:
93-98
栏目:
出版日期:
2017-11-15

文章信息/Info

Title:
Scour Prevention Design of Railway Bridge in Southwest Dangerous Mountainous Area
文章编号:
1674—8247(2017)06—0093—06
作者:
刘发明游励晖
中铁二院工程集团有限责任公司, 成都 610031
Author(s):
LIU Faming YOU Lihui
China Railway Eryuan Engineering Group Co., Ltd.,Chengdu 610031, China
关键词:
山区河流 铁路桥梁 冲刷计算 设计
Keywords:
Key words:rivers in mountainous regions railway bridge scour calculation design
分类号:
U442.3+2
DOI:
10.12098/j.issn.1674-8247.2017.06.019
文献标志码:
A
摘要:
文章对西南艰险山区铁路顺河(江)、跨河(江)桥梁的冲刷计算和桥位选择等方面的问题进行了总结,为山区铁路桥梁设计如何进行冲刷计算和桥位选择提供了一些经验。山区铁路顺河(江)桥梁墩台一般宜设置在受洪水影响较小、流速较低的河滩或河岸附近,不宜设置在水流速度较大的主流处。山区跨河(江)桥梁的桥位布置一般宜选择在河道顺直、河床稳定、水面较窄、水流平稳、水流流向在高低水位时变化不大的河段; 不宜选择在急弯、沙洲、分岔、两河交汇或河床采沙取石严重等处。
Abstract:
Abstract:A series of crucial issues related to the scour calculation and bridge location selection for the railway bridges that go alongside the river and cross the river in southwestern dangerous mountainous regions are concluded in this paper, which gives valuable experiences for the scour calculation and bridge location selection design for the railway bridges in mountainous regions. According to the research in this paper, the riffle area or the area close to the river bank which will be less influenced by the flood is the recommended location for the piers and abutments of bridges that will go alongside the river. In addition, for the bridges that will cross the river, the straight reach section with stable river bed and flow, narrow main channel, and stable flow direction during the water level variation period is a better location than the river section with sharp curves, sandbank cay towheads, bifurcates, river junctions or quarry pits.

参考文献/References:

[1] 铁道部第三勘测设计院.铁路工程设计技术手册:桥渡水文[M]. 北京:中国铁道出版社,1993. Third Survey and Design Institute, MOR. Technical Manual for Railway Engineering and Design: Bridge Hydrology[M].Beijing: China Railway Publishing House,1993.
[2] 铁道部第二勘测设计院.山区铁路桥梁水害的诌见——从宝成铁路略(阳)广(元)段水害中对铁路桥梁勘测设计的认识[Z]. 成都:铁道部第二勘测设计院,1982. China Railway Eryuan Engineering Group Co.,Ltd. The Preliminary Opinions to the Flood Hazard to Bridges at Mountainous Regions——The Knowledge Acquired from Flood Hazard to the Bridges of the Section Between Lueyang and Guanyuan of Baoji-Chengdu Railway[Z]. Chengdu: China Railway Eryuan Engineering Group Co.,Ltd., 1982.
[3] TB 10017-99 铁路水文工程勘测设计规范[S]. TB 10017-99 Code for Survey and Design on Hydrology of Railway Engineering[S].
[4] 高冬光.公路桥涵设计手册——桥位设计[M].北京:人民交通出版社,2001. GAO Dongguang. Design Manual for Highway Bridge and Culvert——Bridge Location Design[M].Beijing: China Communications Press, 2001.
[5] 中铁二院工程集团有限责任公司.新建高速铁路勘察细则[Z].成都:中铁二院工程集团有限责任公司,2010. China Railway Eryuan Engineering Group Co.,Ltd. Detailed Rules of Newly-Constructed High-speed Railway Survey[Z]. Chengdu:China Railway Eryuan Engineering Group Co.,Ltd., 2010.
[6] 中铁二院工程集团有限责任公司.新建铁路勘察细则[Z].成都:中铁二院工程集团有限责任公司,2010. China Railway Eryuan Engineering Group Co.,Ltd. Detailed Rules of Newly-Constructed Railway Survey[Z]. Chengdu:China Railway Eryuan Engineering Group Co.,Ltd., 2010.
[7] 中铁二院工程集团有限责任公司.改建铁路勘察细则[Z].成都:中铁二院工程集团有限责任公司,2010. China Railway Eryuan Engineering Group Co.,Ltd. Detailed Rules of Reconstructed Railway Survey[Z]. Chengdu: China Railway Eryuan Engineering Group Co.,Ltd., 2010.
[8] 游励晖,陈思孝.西南山区铁路桥梁设计的几点思考[J]. 高速铁路技术,2015,6(5): 78-82. YOU Lihui,CHEN Sixiao.Thoughts on Design of Railway Bridge in Southwest Mountain Aear[J].High Speed Railway Technology, 2015,6(5): 78-82.

备注/Memo

备注/Memo:
作者简介:刘发明(1964-),男,高级工程师。
更新日期/Last Update: 2017-12-15